A 1 ppm increase requires 1 gram of available chlorine per 1,000 litres of water. The product dose depends on the pool volume, your test result and the available chlorine percentage on the label.

A pool owner testing free chlorine before adding a treatment

Pool volume alone does not determine a chlorine dose. You also need the current free chlorine reading, the target reading and the product's available chlorine concentration. Raising free chlorine by 1 ppm requires 1 g of available chlorine per 1,000 litres of water; the amount of granules or liquid depends on the strength stated on the label.

Written and edited by: Pool Explained editorial team

Calculating a chlorine dose from pool volume, test results and product concentration
You need a water test result, the pool volume and the available chlorine percentage shown on the product label.
1

How to calculate the dose

First calculate water volume. For a rectangular pool, multiply length by width by average water depth. A pool measuring 6 × 3 m with an average depth of 1.3 m holds approximately 23.4 m³. Large steps or benches reduce the actual volume, but this gives you a starting estimate.

Next, measure free chlorine. As an arithmetic example, increasing a reading from 0.5 ppm to 1.5 ppm means adding 1 ppm. In 23.4 m³, that requires 23.4 g of available chlorine. This is not yet the weight of product to add, and 1.5 ppm is not a suitable target for every pool. Choose the target from your treatment instructions, then account for product concentration.

If the granules contain 65% available chlorine, divide 23.4 g by 0.65. The result is approximately 36 g of product. A 2 ppm increase in the same pool would require twice as much. This illustrates why doses cannot be copied from the packaging of a different product.

With liquid chlorine, check how concentration is stated. Some labels give a percentage; others give available chlorine per litre. If it is unclear, do not guess. Follow the manufacturer's dosing instructions or ask the supplier to confirm the calculation for your pool volume.

Look for available chlorine on the label, not just the product name or total pack weight. If concentration is expressed differently, use the manufacturer's dosing table. The examples here explain the arithmetic; they do not replace instructions for the product you use.

2

Why the daily dose changes

Sunlight breaks down chlorine in an outdoor pool. Demand also increases with warm water, more swimmers, rain, dust, leaves and cosmetics. A dose that was enough during a quiet week may not be enough after a busy day of swimming.

pH affects chlorine performance too. If pH is too high, chlorine works less effectively even when a test shows it is present. Check both readings before a large adjustment. In outdoor pools, monitor stabiliser: too little allows faster chlorine loss in sunlight, while too much makes effective chlorination harder to maintain.

For home pools, the CDC recommends at least 1 ppm free chlorine, or at least 2 ppm when cyanuric acid or stabilised chlorine is used, with pH between 7.0 and 7.8. Your product instructions and equipment requirements may be more specific. Set your target accordingly.

Slow-dissolving tablets are generally for routine chlorination, not rapid correction of a low reading. Do not place a tablet directly on the floor or liner, where it can bleach or damage the surface. Use a floating dispenser or feeder only as permitted by the chemical and equipment instructions.

3

How to add chlorine safely

Keep chlorine in its original, securely closed packaging in a dry, ventilated place, separate from acids, pH reducers and other chemicals. Never mix chlorine types or put chlorine and acid together in a bucket, skimmer or feeder. The mixture can release dangerous gas or react violently.

Test pH and free chlorine before dosing. Take the water sample away from return jets and chemical addition points. Use clean testing equipment and in-date reagents. If the result seems implausible, repeat the test according to its instructions before adding more chemicals.

Add the product exactly as its label describes. Some products need pre-dissolving; others go directly into the pool. Do not substitute your own method. Where pre-dissolving is permitted, use a clean container dedicated to that chemical and follow the stated order for adding water and product.

Keep swimmers out while dosing. Run circulation for the specified time, observe the waiting period and test again. Swimming can resume only when chlorine and pH are within the required ranges and the label's waiting time has passed.

4

When shock treatment is needed

Shock treatment is used when chlorine needs to rise quickly, for example to treat algae, address contamination after very heavy use or deal with a chloramine problem confirmed by testing. It is not a dose to add blindly every week. The amount depends on the reason for treatment, current readings, stabiliser and the product.

A strong chlorine smell and stinging eyes often indicate chloramines rather than excess free chlorine. Test free and total chlorine and act on the readings. Ventilation matters in indoor pools too. Smell alone cannot determine the dose.

For green water, shock chlorination is only part of the treatment. Brush the walls and floor, monitor and clean the filter, and remove settled debris. If the water is transparent but turned green or brown after chlorine was added, metals may be responsible. More chlorine can intensify that colour and cause stains.

After shock treatment, keep everyone out until the label's waiting time has passed and a fresh test confirms acceptable readings. Do not rely on smell or appearance. Record the dose and the next test result so you have useful information from your own pool for future treatments.

The calculation

How to calculate a chlorine dose

You need three figures: the pool's water volume, its current free chlorine reading and the product's available chlorine percentage. Without all three, you would be guessing.

1. Find the pool's water volume

Calculate the actual volume of water in cubic metres. One cubic metre equals 1,000 litres.

2. Work out the required increase

Subtract the measured free chlorine from your target level. The difference is the increase needed, in ppm.

3. Calculate the available chlorine needed

Multiply the water volume in cubic metres by the required increase in ppm. This gives the grams of available chlorine needed, before allowing for the strength of your product.

4. Calculate the product dose

Divide that amount by the product's available chlorine fraction: for example, use 0.65 for a product containing 65% available chlorine.

Worked example

A chlorine dose for a 30 m³ pool

To raise free chlorine by 1 ppm, you need 30 grams of available chlorine. With a product containing 65% available chlorine, that works out at roughly 46 grams of product.

Pool volume30 m³
Measured free chlorine0.5 ppm
Target free chlorine1.5 ppm
Required increase1.0 ppm
Available chlorine needed30 g
Product with 65% available chlorineabout 46 g of product

Safe dosing

Before you add chlorine

Read the label, test the water and prepare the required protective equipment. Never mix different pool chemicals in the same container or feeder.

  1. 1Read the full label. Check the available chlorine percentage, application method and minimum waiting time before swimming.
  2. 2Test free chlorine and pH before dosing. Take the sample away from return jets and chemical addition points.
  3. 3Wear the protective equipment specified on the label and open the product in a well-ventilated area.
  4. 4Never mix different types of chlorine, or chlorine with acid or other pool chemicals, in the same container or feeder.
  5. 5Apply the product only as the manufacturer instructs, with the required circulation and no swimmers in the water.
  6. 6Wait for the time stated on the label, test again and only then decide whether another adjustment is needed.

Practical answers

Chlorine dosing: common questions

How much chlorine is needed for 10 cubic metres of water?

Raising free chlorine by 1 ppm in 10 m³ requires 10 grams of available chlorine. For a product containing 65% available chlorine, the calculated dose is about 15.4 grams. Follow the product's application instructions and test again afterwards.

How much chlorine is needed for 30 cubic metres of water?

A 1 ppm increase requires 30 grams of available chlorine. With a 65% product, that is about 46 grams of product. A 2 ppm increase requires twice as much, but always check the label for the application method and maximum permitted dose.

Should you add chlorine every day?

Do not add a fixed daily amount without testing. Sunlight, temperature, swimmers, rain, covers and the type of chlorine all affect demand. Test results tell you whether an adjustment is needed. A slow-dissolving product can maintain chlorine where the pool has a suitable feeder.

Why does the test still read zero after adding chlorine?

Chlorine may be used up quickly by contamination after heavy use or a storm. Other possibilities include an incorrect pool volume, poor circulation or expired test reagents. Very high chlorine can also produce a falsely low or zero reading with some tests. Check the measurement, pH and circulation before adding another dose.

When can you swim after adding chlorine?

Wait until the label's minimum time has passed and the pump has run as instructed. The bottom must be clearly visible, and a fresh test must show acceptable free chlorine and pH levels.

Can you put a chlorine tablet directly in the pool?

Do not leave a tablet on the liner, steps or pool floor. The concentrated chlorine can bleach or damage the surface. Use a suitable floating dispenser or feeder, following both the chemical and equipment instructions.

Related topics